Process | Timeline |
1.3d modeling | 3-5 working days |
2.Prototype Making | 5-7 working days |
3.Mold Making | 20-25 working days |
4.Pre-production sample Making | 5-7 working days |
5.Toy Parts Production | 3-5 working days |
6.Color Painting | 1-2 working days |
7.Parts assembling | 5-7 working days |
8.Packaging Box Making | 7-10 working days and can be done simultaneously |
9.Quality Control | Quality control throughout whole process |
10.Packing | 3-5 working days |
11.Quality Inspecting | 1-2 working days |
12.Shipping | After paying the balance |
Note:The production process of a toy making project takes approximately 2 to 3 months of production time | |
Item | Payment Policy |
Sample fee | 100% be paid before start |
Smaple freight | be paid before shipping |
Molds cost | 100% be paid before make molds |
Pre-production sample freight | be paid before shipping |
Advance payment for mass production | 50% deposit be paid before mass production |
Final payment for bulk goods | 50% balance be paid before shipping |